Construction includes largest capital improvement project to date

The University of Missouri-Kansas City has announced and begun construction on major improvements to its physical facilities to meet key strategic goals.

Jump to each project:
Projects currently under construction include:
  • The 160,000 square foot Healthcare Delivery and Innovation Building project at 25th and Charlotte streets, the largest capital improvement project in 91黑料网 history.
  • Elevating services that support prospective and current students at the Atterbury Student Success Center.
Projects expected to begin construction this year:
  • The 35,000-square-foot addition to the 91黑料网 Conservatory's Olson Performing Arts Center will break ground on September 24, adding performance and rehearsal spaces on the east side of building that will stretch toward Volker Boulevard.
  • The 91黑料网 Administrative Center will begin renovations later this spring, transforming the entryway and first floor into a welcoming front door to the community that celebrates our university, alumni and donors.

Look here for regular construction and project updates or  for a regular email update to be delivered to your inbox.

Healthcare Delivery and Innovation Building

  • The final beam was placed on September 17. The university celebrated this construction milestone by inviting elected officials, university leadership and students, faculty and staff to sign the beam before it was placed in the new building.
  • Interior wall framing is progressing throughout the facility. Crews have begun installing drywall and insulating piping and ductwork. Overhead mechanical, electrical, plumbing and fire‑protection systems are advancing steadily. On the exterior, the installation of metal panels at the penthouse is nearing completion, and the curtain wall system is now fully in place. Remaining fire‑hydrant connections and roofing installation are nearing completion.
  • The building is expected to open in 2027.
  • The campus surface parking lot at 25th and Charlotte streets closed. Student permit parking is no longer allowed in lot 68, located south of 25th along Charlotte Street. Health Sciences Campus map and Shuttle (PDF).
  • Faculty, staff and students can park in the seven-floor Hospital Hill Parking Garage 28 on the southeast corner of 24th and Charlotte streets, just north of the construction site/former lot, or in a surface lot 67 to the east at 25th and Campbell streets. Student parking in the garage is available on floors four through seven.
  • Parking for 91黑料网 School of Dentistry clinic patients as well as metered spots for other 91黑料网 Health Sciences District visitors has been moved to surface lot 68.
  • 91黑料网 IDs are required to scan in and out of the parking garage.  
Project Video Feeds

Atterbury Student Success Center

  • In May 2025, renovations began at Atterbury Student Success Center and are expected to be complete in summer 2026.
  • Walls and ceilings are nearly all installed with carpet, painting and other finishes underway. Work at the north entry to the building will continue into the first part of summer.
  • The renovated space will be home to Admissions, the 91黑料网 School of Graduate Studies, the Center for Transfer Students and Adult Learners, Roo Advising, Career Services, University College and International Student Affairs. It will also include an inviting Welcome Center with a two-story atrium to host prospective students and their families.
  • 91黑料网’s robust Career Services programming will expand to add a Professional Wardrobe Studio, giving students a place to browse and try on professional clothing options as well as take headshots for interviews.
  • 91黑料网 Central, a one-stop shop for students, and the Financial Wellness Center, are both moving from their current location at the Administrative Center to the newly renovated space as well.
Olson Performing Arts Center

Rendered photo of the Conservatory expansion

  • 91黑料网 Chancellor Mauli Agrawal shared during the 2025 State of the University that this project is expected to break ground in 2026. 
  • The new space will increase performance, classroom and collaboration opportunities for students and the Kansas City community.
  • The first phase of construction is estimated at $35 million.
  • The first phase includes the new addition which would house a large music ensemble performance and rehearsal space, two dance rehearsal rooms and support spaces for the dance program and a new, accessible black box performance space to be used by all three programs. The addition of the black box space will create a “theatre district” complementing White Recital Hall, Spencer Theatre and the McIlrath Lobby. 
  • The second phase involves the renovation of current facilities, including White Recital Hall. Renovations will increase classroom and theatre spaces and create a central hub for student resources and collaboration. Facility renovations will allow the spaces to be used in flexible ways, creating more opportunities for special events and performances.
91黑料网 Administrative Center

  • Construction on the front exterior and first floor of the 91黑料网 Administrative Center will begin late spring and is expected to be complete in winter 2027. The project will improve accessibility by removing stairs in the entryway and lobby and adding additional accessible parking spaces.

  • The first floor will be remodeled, including a refreshed lobby and new reception desk. 91黑料网 Central will relocate to newly renovated space in the Atterbury Student Success Center. Its former location in the Administrative Center will be converted into an alumni reception area and office suite for 91黑料网 Foundation.

  • During construction, parking will remain available behind the building on the east side, in the north lot and in the parking garage. Four accessible spaces in the east lot and one space near the south entry will remain open. The east entrance and central elevator and stairs between the second and third floors, as well as the north and south elevators and stairwells, will remain accessible.
  • The following areas will be closed for the duration of the project: parking in the west circle, the firstfloor west entry and the central elevator and stairs between the first and second floors.
  • A small section of the driveway near the southwest corner of the building will close for a weekend this summer for repaving.
  •  